Mission: STS-122 – 24th International Space Station Flight – Columbus Module
Vehicle: Atlantis (OV-104)
Location: Orbiter Processing Facility Bay 1
Launch Date: Targeted for Dec. 6, 2007
Launch Pad: 39A
Crew: Frick, Poindexter, Schlegel, Eyharts, Love, Melvin and Walheim
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles
In Orbiter Processing Facility bay No. 1, Atlantis has been placed on the orbiter transporter in preparation for rollover to the Vehicle Assembly Building. The transfer is planned to begin at 7 a.m. Saturday, Nov. 3.
Activities to attach Atlantis to the external tank/solid rocket booster stack will start once the orbiter is in the Vehicle Assembly Building by attaching the lifting sling. The shuttle interface test to verify that all the space shuttle elements are working as a fully integrated launch vehicle will begin on Nov. 7. Rollout from the VAB to Launch Pad 39A is scheduled for 4 a.m. Nov. 10.